| Project Name: | I-70 & Ward Road, Intersection Improvements |
|---|---|
| Project ID: | IM 0703-310 |
| Owner/Agency: | Colorado Department of Transportation |
| Work Description: | Project consists of widening of 44th avenue to accommodate new ramps for I-70, as well as asphalt resurfacing of I-70 from Kipling to Colfax. |
| Start Date: | January 2010 |
| Completion Date: | July 2011 |
| Project Information: | 303-996-7261 or kbrown@apc.us.com |
|
For the month of July, lane closures on 44th ave. can be expected for the installation of concrete along the north side of 44th ave. Work hours will be from 7:00am to 5:00 pm, Monday through Friday. |
|
|
Project Name:
|
SH 128: McCaslin to Eldorado
|
|
Project ID:
|
STA 128A-005
|
|
Owner/Agency:
|
Colorado Department of Transportation
|
|
Work Description:
|
Asphalt resurfacing on SH 128 from McCaslin to Eldorado
|
|
Start Date:
|
August 2010
|
|
Completion Date:
|
November 2010
|
|
Project Information:
|
720-974-6621 or jmkeller@apc.us.com
|
|
Minor traffic delays can be expected Monday through Friday.
|
|
|
Project Name:
|
SH 72 Overlay & Widening
|
|
Project ID:
|
STA 072A-032
|
|
Owner/Agency:
|
Colorado Department of Transportation
|
|
Work Description:
|
Project consists of shoulder widening and asphalt resurfacing on SH 72 from SH 93 West approx. 2.5 miles
|
|
Start Date:
|
August 2010
|
|
Completion Date:
|
November 2010
|
|
Project Information:
|
720-974-6620 or bshafer@apc.us.com
|
|
Minor traffic delays can be expected Monday through Friday during daytime work hours.
|
|