Past Projects

US 40, Kipling to Sheridan
- Three mile resurfacing project on W. Colfax in Lakewood, CO
- 15,000 Tons HMA
- Owner/Agency: Colorado Department of Transportation
- Prime Contractor: APC
- Start Date: June 2009
- Completion Date: October 2009
Applewood Baptist Church
- New parking lot construction in Wheat Ridge, CO
- 6,000 Tons HMA
- Owner: Applewood Baptist Church
- Prime Contractor: APC
- Start Date: June 2009
- Completion Date: October 2009
JCMD Phase 1 Infrastructure Project
- Construction of new roadway in Arvada, CO
- 60,000 Tons HMA
- Owner/Agency: Jefferson Center Metropolitan District
- Prime Contractor: Tarco, Inc.
- Start Date: July 2008
- Completion Date: August 2009
Mother Cabrini Shrine Road
- Two mile resurfacing project in Golden, CO
- 4,000 Tons HMA
- Owner: Mother Cabrini Shrine
- Prime Contractor: APC
- Start Date: May 2009
- Completion Date May 2009
US 6, Golden West Overlay
- Resurfacing project through Clear Creek Canyon
- 12,000 Tons SMA, 1,700 Tons HMA
- Owner/Agency: Colorado Department of Transportation
- Prime Contractor: APC
- Start Date: May 2007
- Completion Date: July 2007
I-70, Georgetown East
- Resurfacing project on I-70 from Idaho Springs to Georgetown with emergency repair over abandoned mine shaft
- 24,000 Tons SMA, 7,000 Tons HMA
- Owner/Agency: Colorado Department of Transportation
- Prime Contractor: APC
- Start Date: April 2006
- Completion Date: October 2006
Central City Parkway
- Eight miles of new parkway construction
- 125,000 Tons HMA
- Prime Contractor: Ames Construction, Inc.
- Start Date: June 2003
- Completion Date: November 2004
DIA International Runway
- New construction of asphalt pavement shoulders for International Runway at Denver International Airport
- 100,000 Tons HMA
- Owner/Agency: Denver International Airport
- Prime Contractor: Interstate Highway Construction
- 2002-2003